Permits with Well Pad Development in the Permian Down 26% in April 2022

By Greg Tsichlis - May 13, 2022

April 2022, in the Permian Basin, DirtWork AlertTM detected 317 permits on 250 well pads currently under construction or completed. The number of permits with active pad development fell by 25.6% vs March 2022.

Conversely, the total number of pads associated to these permits increased from 143 in March to 250 in April (+74.8%).

Many drilling permits are filed but many are never drilled. It is important to identify those permits where drilling is actually going to take place. In many cases, well pads and ponds are being constructed before the permit is filed. DirtWork Alert can identify these activities occuring ahead of permits.

Permian drilling permits drop but well pads increase in April 2022

Here is a list of the top 10 operators driving this activity (along with associated pad detections):

  • Pioneer (21)
  • Diamondback (16)
  • Birch (14)
  • Oxy (9)
  • XTO (9)
  • Advance (6)
  • Avad (5)
  • Blackbeard (5)
  • Crownquest (5)
  • Endeavor (5)

New well pad construction in the Permian March 2022 This map is an example of Sourcenergy geospatial data. It shows site activity locations (blue dots) along with TX SRA (red lines) and NM seismic regions (yellow) and fault lines (black lines). Source: Sourcenergy

 

For additional details on operators, surface owners and locations of this pre-drill (and pre-permit) activity please contact us: [email protected]

REQUEST A DEMO

DirtWork Alert uses satellite technology in combination with permit data and applies artificial intelligence & machine learning to identify upstream activity earlier and more accurately than any other source.  And in many instances these pre-drilling activities are detected before a permit has been filed.