Allied has secured Oil Cat Energy Services for the filing of the necessary Underground Injection Permit for saltwater injection for the Green lease. Allied will use Oil Cat Energy Services as the go-to solution for surveying the plat for the precise injection well location, for securing the drilling permit for the injection well, for engineering services and consulting, and workover engineering for new production well set ups for increased fluid production rates.
Allied has begun dozier work for road construction, location clearing/cleaning, and reserve pit building at the Palo Pinto Well #1 location.
Allied is reconnecting electricity on the Palo Pinto #1 and #2 Wells next week and will be turning on the pump on the Palo Pinto #1 Well to test the fluid levels and flow rates.